aviation-bluet  Aviation / Architectural / Engineering Services

Center Lighting Vault Relocation (Design)

Details

A Blue Printer Icon to Print Anything A Small Blue Download Icon
Add to Calendar 2025-12-31 2025-12-31 Center Lighting Vault Relocation (Design)

The Center Lighting Vault Relocation Project will relocate the existing lighting vault, located at the Mid-Field area at CLT Airport to a new proposed location. The project will consist of site work, building work, site utilities, and airfield lighting circuitry.

The selected Final Design Engineer or Engineer of Record (EOR or Consultant) will produce Construction Documents to be issued for competitive bidding of one or multiple construction packages, followed by Conformed or Released for Construction Plans issued to the responsive or responsible bidder for Construction.  The design and documents are to be based on Preliminary Design or bridging documents prepared by the Owner’s Master Civil Engineer (Aviation Consulting Engineers, LLC, or ACE).  The Preliminary Design effort will include completion of the Design Geotechnical Subsurface Investigation, preliminary design plans to a 30% level of completion, pavement design, and preliminary surveys.  Final Design surveys, including pavement tie-ins, etc. will be the responsibility of the Consultant.

Posting Number 2025-Q4(Oct-Dec)-AVI-8874

Anticipated Posting Date 2025-12-31

Commodity Code(s): 92517, 92536

The Center Lighting Vault Relocation Project will relocate the existing lighting vault, located at the Mid-Field area at CLT Airport to a new proposed location. The project will consist of site work, building work, site utilities, and airfield lighting circuitry.

The selected Final Design Engineer or Engineer of Record (EOR or Consultant) will produce Construction Documents to be issued for competitive bidding of one or multiple construction packages, followed by Conformed or Released for Construction Plans issued to the responsive or responsible bidder for Construction.  The design and documents are to be based on Preliminary Design or bridging documents prepared by the Owner’s Master Civil Engineer (Aviation Consulting Engineers, LLC, or ACE).  The Preliminary Design effort will include completion of the Design Geotechnical Subsurface Investigation, preliminary design plans to a 30% level of completion, pavement design, and preliminary surveys.  Final Design surveys, including pavement tie-ins, etc. will be the responsibility of the Consultant.

Requirements

Last Updated: 02/20/23
Insurance Requirements+
Estimated Total Value+
Contract Term+

Follow This Opportunity!

Get updates on this opportunity by following the hashtag on Twitter or Facebook!

Logo of Twitter with Blue Background Logo of Facebook with Dark Blue Background

For Questions, Contact:

Gary Peeples

City Contact

ghpeeples@cltairport.com