Overflow Lots 1 and 2 Crack Sealing (Construction)

This project will consist of approximately 75,000 LF (not to exceed) of crack sealing in Overflow Parking, Lots 1 & 2.

The contractor will properly remove/clean vegetation and debris from cracks and hot pour crack seal in running/random cracks throughout each lot.
Heavily alligator cracked areas will be excluded in lieu of asphalt patching under separate contract.  These areas will be identified on site prior to commencement of work.   Cleaning and sealing of concrete at concrete/asphalt joints (at curbs and islands) are not included.
Parking Lots will be empty and clear of vehicles during this work

Overflow Lots 1 & 2 Asphalt Patching (Construction)

This project will consist of Asphalt Patching in Overflow Parking for Lots 1 & 2.:

1. Approximately 7,500 square feet of asphalt patching at 2” depth per NCDOT Standards
2. Approximately 3,200 square feet of asphalt patching at 10.5” depth per standard below.

Compact 6” ABC stone will be included, as needed, estimated at 100 tons.

These areas will be identified/confirmed on site prior to commencement of work.  Parking lots will be empty and clear of vehicles during this work.

FY22 New Construction Services Miscellaneous Contract #1

This solicitation will provide for ongoing construction services for the installation of large water and sewer services as requested for commercial/residential use.  The work also includes opportunities for installation of short street main extensions (< 100′), fire hydrant relocations and dismantlements as related to new requests. 

FY22 New Services Miscellaneous Contract #2 – CANCELLED

Ongoing contract for installation of large water and sewer services as requested for commercial/residential use.  Also includes opportunities for short street main extensions (< 100′), fire hydrant relocations and dismantlements as related to new requests

Westbourne Storm Drainage Improvement Project

The project area covers approximately 20 acres and is roughly bounded by Old Plank Road to the north, Larkhaven Road to the east, Westbourne Drive to the west, and Bellhaven Boulevard to the south. The project includes storm drain improvement including culvert replacements, repair of aging and deteriorating storm drains by way of pipe system upgrades, and channel stabilization improvements. The project also includes water line upgrades and sanitary sewer relocations along with road resurfacing and seeding in affected project areas.

Elvis Storm Drainage Improvement Project

This project consists of two culverts in series under Cedarbrook Drive and Denbur Drive. Both culvert crossings consist of triple barrel corrugated metal pipe systems. This is a project that was identified by the asset management team and both culvert crossings are actively failing, and preliminary calculations show that the culverts are also undersized.

Bonwood Storm Drainage Improvement Project

The project involves analysis of existing conditions to determine areas suitable for improvement, planning analysis of improvement alternatives, and the design and construction of the needed improvements in the Bonwood Storm Drainage Improvement Project (SDIP) area.

The Bonwood SDIP is bordered by Wendover Road to the south, Canterbury Drive to the east and Chadsford Place to the west. This project is within a drainage area of approximately 124 acres and the improvements include paving, curb and gutter, culvert replacements, pipe system lining/repair and upgrades, and minor open channel improvements.

Chatham Storm Drainage Improvement Project

The purpose and need for this construction project is to improve the storm drainage infrastructure (i.e. pipe systems and culverts) to reduce flooding and to enhance degraded stream reaches to reduce erosion and improve water quality.  This project is under review.  Location and project details will be provided after review is complete.