Uptown Cycle Track

The project includes implementation of a two-way separated cycle track in Uptown Charlotte along portion of 5th and 6th street. It will provide a connection between Little Sugar and Irwin Creek Greenways. The cycle track will be constructed mostly within the existing roadway, currently used as vehicular travel lanes and on‐street parking. Traffic signals will be modified and an at‐grade crossing of the Lynx Blue Line is required. Work includes the construction of cycle tracks and ramps, concrete medians, pavement markings, milling, resurfacing, traffic signals and signage.

Tuckaseegee Berryhill Thrift Roundabout

The project will replace the signalized intersection with a roundabout. Project will also provide sidewalks, curb and gutter, driveways, concrete island, wheel chair ramps, retaining wall, storm drainage, asphalt pavement, pavement markings and signage and utility relocation.

FY2020 A-D Storm Water Repair and Improvement

Specialized stormwater services

 

Archived solicitations link

FY2020A -https://charlottenc.gov/DoingBusiness/Pages/SolicitationDetails.aspx?ID=1120

FY2020B

https://charlottenc.gov/DoingBusiness/Pages/SolicitationDetails.aspx?ID=1121

FY2020C

https://charlottenc.gov/DoingBusiness/Pages/SolicitationDetails.aspx?ID=1158

FY2020D

https://charlottenc.gov/DoingBusiness/Pages/SolicitationDetails.aspx?ID=1159

Wilkinson Boulevard ITS Phase 2

This project will install single‐mode fiber optic cable installed in new directionally bored, hand dug and trenched conduit, existing conduit and aerial attachments to poles. It will remove existing copper communication cables. This project includes entrances and interconnect equipment for existing traffic signal control cabinets and the installation of traffic management cameras. This project also includes fiber optic cable splicing, testing, Ethernet communications equipment, traffic management camera equipment and other related activities.

Graham Street Extension Intelligent Transportation Systems

This project will install single‐mode fiber optic cable in existing conduits. This project includes entrances and interconnect equipment for existing traffic signal control cabinets and the installation of traffic management cameras. This project also includes fiber optic cable splicing, testing, Ethernet communications equipment, traffic management camera equipment and other related activities.

Sardis Road Intelligent Transportation System (ITS)

This project will install single‐mode fiber optic cable installed in new directionally bored, hand dug and trenched conduit, existing conduit and aerial attachments to poles. This project includes entrances and interconnect equipment for existing traffic signal control cabinets and the installation of traffic management cameras. This project also includes fiber optic cable splicing, testing, Ethernet communications equipment, traffic management camera equipment and other related activities.

West Boulevard ITS

This project will install single‐mode fiber optic cable installed in new directionally bored, hand dug and trenched conduit, existing conduit and aerial attachments to poles. This project includes entrances and interconnect equipment for existing traffic signal control cabinets and the installation of traffic management cameras. This project also includes fiber optic cable splicing, testing, Ethernet communications equipment, traffic management camera equipment and other related activities.