CMGC HVAC Replacement Construction Manager-at-Risk

City of Charlotte (City) is seeking to acquire the services of a Construction Manager-at-Risk (CMR) for the Charlotte-Mecklenburg Government Center HVAC Replacement Project (Project). The Guaranteed Maximum Price (GMP) estimate for the Project is $20,400,000 (the Target GMP Range).

The City has selected CMTA, Inc. (Mechanical Engineer) to provide mechanical design services for replacement of the HVAC system in the existing 14 story, nominally 440,000 square foot facility located at 600 East 4th Street (parcel number 223-132-08). This facility is known as the Charlotte-Mecklenburg Government Center (CMGC) and houses several City and County Departments.

 The CMR shall contract directly with the City for all construction; shall publicly advertise as prescribed in NCGS 143-129; and shall prequalify and accept all bids from first-tier subcontractors for all construction work under this section. The CMR shall use the prequalification process determined by the City in accordance with NCGS 143-135.8.

Construction will be phased and start in August 2021, and is anticipated to be complete in August 2025.  The facility will remain open and in operation during the construction period.

This posting is live at – https://charlottenc.gov/DoingBusiness/Pages/SolicitationDetails.aspx?ID=1527